Budgeting — Purposes, Budgetary Control, the Master Budget & Functional Budgets to the Cash Budget
What a budget is, its purposes and functions, steps in budgetary control, types of budgets and master budget components, sales forecasting, and the full LFT chain (sales → production → material usage → material purchases → labour → cash budget), plus limitations.
▶Lecture videos
Click any timestamp — here or inside the notes — to jump the video to that moment. Your position is remembered.
Budgeting
Definitions and functions, then a complete worked example (LFT company, grades A and B, wood and glass) through every functional budget to the cash budget.
00:02Introduction01:19What a budget is: a quantifiable action plan03:51Functions of budgets07:36Types: functional, master and cash budgets08:24Sales budget10:10Production budget: the format and its logic14:37LFT example: sales and production budgets18:34Material usage budget20:11Material purchases budget22:21LFT: material usage (wood and glass)27:26LFT: material purchases29:21Direct labour budget30:43LFT: labour budget (Rs 200/hour, 4 and 6 hours)32:05Cash budget33:00LFT: cash budget36:08Limitations of budgeting1What is a budget?
- Budget: a detailed plan, expressed in quantitative terms, that specifies how an organisation will acquire and use resources during a particular period. In the lecture's words, "a quantifiable action plan for a specified time period" 01:19.
- Budgetary control: a system of planning and controlling cost.
- Budgets flow from strategic planning. Every enterprise has goals: profitability, growth, public service.
- Strategy aims at achieving and maintaining a competitive advantage through critical success factors: the key strengths most responsible for the organisation's success.
- A budget is built on past activities: last year's figures plus planned changes 02:29.
Purposes & functions of budgeting 03:51
| Purpose | Meaning |
|---|---|
| Planning | Plan annual operations: what and how much to produce and sell |
| Facilitating communication & coordination | Departments share information, giving harmony between departments |
| Allocating resources | Scarce resources go where they're needed |
| Managing financial & operating performance (control) | Compare progress against the budget; take corrective action |
| Evaluating performance & providing incentives | Motivates managers towards organisational goals |
Steps in budgetary control
- Establish budgets
- Measure actual performance
- Compare actual with budget
- Analyse causes of variances & report
2Types of budgets
| Budget | What it is |
|---|---|
| Master budget | A comprehensive set of budgets covering all phases of operations for a period |
| Operational budgets | How operations will meet demand, using material, labour and overhead |
| Financial budget | How the organisation will acquire its financial resources |
| Capital budget | Plan for acquiring (and disposing of) capital assets |
| Cash budget | Expected cash receipts and disbursements |
The lecture groups them as functional budgets → master budget → cash budget 07:36.
Master budget components:
- Operational:
- sales budget
- production budget
- direct material budget
- direct labour budget
- overhead budget
- budgeted cost of goods manufactured and sold
- selling, general and admin budget (R&D, marketing, customer service)
- Financial:
- capital budget
- cash budget
- budgeted income statement
- budgeted statement of financial position
- budgeted statement of cash flows
Sales forecasting: the starting point
The sales budget drives everything else. The factors are:
- past sales levels and trends
- general economic trends
- economic trends in the industry
- other factors expected to affect industry sales
- political and legal events
- intended pricing policy
- planned advertising and promotion
- expected actions of competitors
- new products planned by the company or others
- market research studies
3The functional budgets: formats
Production (units) = Budgeted sales + Closing finished goods − Opening finished goods
Material usage = Production units × Material per unit
Material purchases = Usage + Closing raw materials − Opening raw materials (× cost per unit)
Labour budget = Production units × Hours per unit × Rate per hour
Why subtract opening and add closing? Opening inventory is already made, so we don't produce it again. Closing inventory must also be made this period 13:53.
| Q1 | Q2 | Q3 | Q4 | Year | |
|---|---|---|---|---|---|
| Sales units | 15,000 | 5,000 | 10,000 | 20,000 | 50,000 |
| × Rs 12 | 180,000 | 60,000 | 120,000 | 240,000 | 600,000 |
| Units produced | 14,000 | 5,500 | 11,000 | 19,500 | 50,000 |
| × 0.2 labour hours | 2,800 | 1,100 | 2,200 | 3,900 | 10,000 |
| × Rs 10 per hour | 28,000 | 11,000 | 22,000 | 39,000 | 100,000 |
4Full worked example: LFT company
- Sales & production budgets 14:37
Data:
| Grade A | Grade B | |
|---|---|---|
| Expected sales (units) | 50,000 | 10,000 |
| Selling price | Rs 6,000 | Rs 8,000 |
| Opening finished goods | 1,000 | 500 |
| Target closing finished goods | 11,000 | 500 |
Sales budget:
| A | B | Total | |
|---|---|---|---|
| Units × price | 50,000 × 6,000 | 10,000 × 8,000 | |
| Revenue | 300m | 80m | 380m |
Production budget:
| A | B | |
|---|---|---|
| Sales units | 50,000 | 10,000 |
| Less: opening finished goods | (1,000) | (500) |
| Add: closing finished goods | 11,000 | 500 |
| Production | 60,000 | 10,000 |
- Material usage & purchases 22:21
Per unit:
- wood: 12 boards for both grades, Rs 70 per board
- glass: A 6 sq ft, B 8 sq ft, Rs 100 per sq ft
Inventories:
- wood: opening 70,000, closing 80,000
- glass: opening 60,000, closing 20,000
| Usage | Wood (boards) | Glass (sq ft) |
|---|---|---|
| Grade A: 60,000 × 12 / × 6 | 720,000 | 360,000 |
| Grade B: 10,000 × 12 / × 8 | 120,000 | 80,000 |
| Total usage | 840,000 | 440,000 |
| Value (× 70 / × 100) | Rs 58.8m | Rs 44m |
| Purchases | Wood | Glass |
|---|---|---|
| Usage | 840,000 | 440,000 |
| Less: opening | (70,000) | (60,000) |
| Add: closing | 80,000 | 20,000 |
| Purchase quantity | 850,000 | 400,000 |
| Purchase cost | Rs 59.5m | Rs 40m |
Usage and purchases differ because of the inventory adjustments 29:21.
- Direct labour budget 30:43
Rs 200 per labour hour. A uses 4 hours and B uses 6 hours per unit.
| A | B | Total | |
|---|---|---|---|
| Production | 60,000 | 10,000 | |
| Hours | 240,000 | 60,000 | 300,000 |
| Cost × 200 | 48m | 12m | 60m |
- Cash budget 33:00
Assumptions:
- opening cash Rs 3m
- all sales are cash sales
- material purchases are paid 100% within the year
- labour is paid in the year
- overheads are paid in cash
| Rs m | |
|---|---|
| Opening balance | 3.0 |
| Receipts: cash sales | 380.0 |
| Payments: material purchases (59.5 + 40) | (99.5) |
| Direct labour | (60.0) |
| Overheads | (55.0) |
| Total payments | (214.5) |
| Net surplus (380 − 214.5) | 165.5 |
| Closing balance (165.5 + 3) | 168.5 |
- The question says overheads of Rs 50m, but the solution uses Rs 55m (that's what gives 214.5). With 50m, payments = 209.5, surplus = 170.5, and closing = 173.5.
- The video says the closing balance is 186.5m. That's an arithmetic slip: 165.5 + 3 = 168.5m.
Learn the method; check the numbers yourself.
5The cash budget: rules
- It's prepared weekly or monthly so management can deal with shortages (arrange overdrafts or loans) or surpluses (invest them).
- Only actual cash receipts and payments are included.
- Depreciation is always excluded: it's not a cash flow.
- Credit sales and purchases still outstanding at period end are excluded. Include cash when it's received or paid, e.g. a 30-day credit sale in March is received in April.
- The closing balance of period 1 = the opening balance of period 2.
Defaults: "other payments" = glass Rs 40m + overheads Rs 55m, which reproduces the 168.5m closing cash.
6Limitations of budgeting 36:08
- Based on estimates and assumptions, so they lack accuracy.
- Preparation takes time, cost and management effort.
- Lack of flexibility: once fixed, budgets aren't changed for unexpected events (e.g. a COVID lockdown). This can demotivate employees who see the targets as unachievable 37:33.
- Budgets can encourage budgetary slack and "spend it or lose it" behaviour.
Expect:
- Define a budget and budgetary control.
- Give the purposes and functions of budgets.
- List the steps in budgetary control.
- Name the master budget components.
- List sales forecasting factors.
- Prepare sales, production, material usage and purchases, labour and cash budgets. Remember the opening and closing stock adjustments. In the cash budget, exclude depreciation and account for credit timing.
- Give the limitations.
7Practice questions (course paper)
Timing rules:
- Customers pay two months after the sale
- Suppliers are paid two months after the purchase
- Wages are paid the next month
- Other expenses are paid one month late
- The machine is paid in 5 × 5,000 instalments from January
- A dividend of 10,000 is paid in April
| Jan | Feb | Mar | Apr | |
|---|---|---|---|---|
| Opening balance | 15,000 | 18,985 | 23,795 | 22,975 |
| Receipts from debtors | 30,000 (Nov) | 35,000 (Dec) | 25,000 (Jan) | 30,000 (Feb) |
| Total available | 45,000 | 53,985 | 48,795 | 52,975 |
| Creditors | 15,000 | 20,000 | 15,000 | 20,000 |
| Wages | 3,200 | 2,500 | 3,000 | 2,400 |
| Manufacturing, admin, selling (previous month) | 2,815 | 2,690 | 2,820 | 2,890 |
| Machinery instalment | 5,000 | 5,000 | 5,000 | 5,000 |
| Dividend | — | — | — | 10,000 |
| Total payments | 26,015 | 30,190 | 25,820 | 40,290 |
| Closing balance | 18,985 | 23,795 | 22,975 | 12,685 |
Sales are read as Jan 90,000 · Feb 135,000 · Mar 220,000 · Apr 320,000 (the PDF's table is jumbled), and all sales are assumed to be on credit. Customers pay 25% in the month of sale, 50% the next month and 25% the month after.
| Jan | Feb | Mar | Apr | |
|---|---|---|---|---|
| Jan sales 90,000 | 22,500 | 45,000 | 22,500 | |
| Feb sales 135,000 | 33,750 | 67,500 | 33,750 | |
| Mar sales 220,000 | 55,000 | 110,000 | ||
| Apr sales 320,000 | 80,000 | |||
| Receipts | 22,500 | 78,750 | 145,000 | 223,750 |
Materials cost 40% of sales: 36,000 · 54,000 · 88,000 · 128,000, with May at 160,000. Closing stock is half of next month's needs, and suppliers are paid one month later.
| Jan | Feb | Mar | Apr | |
|---|---|---|---|---|
| Materials used | 36,000 | 54,000 | 88,000 | 128,000 |
| + closing stock (½ of next month) | 27,000 | 44,000 | 64,000 | 80,000 |
| − opening stock | 0 | (27,000) | (44,000) | (64,000) |
| Purchases | 63,000 | 71,000 | 108,000 | 144,000 |
| Payment (one month later) | 0 | 63,000 | 71,000 | 108,000 |
8Quick revision sheet
| Concept | Remember it as |
|---|---|
| Budget | Quantified plan for acquiring and using resources over a period |
| Budgetary control | System of planning and controlling cost |
| Purposes | Plan · coordinate and communicate · allocate · control · evaluate and motivate |
| Control steps | Set → measure → compare → analyse variances and report |
| Master budget | All the budgets together → budgeted income statement and balance sheet |
| Production | Sales + closing FG − opening FG |
| Purchases | Usage + closing RM − opening RM |
| Labour | Production × hours × rate |
| LFT answers | Sales 380m · production A 60k, B 10k · wood 850k boards = 59.5m · glass 400k = 40m · labour 60m |
| Cash budget | Opening + receipts − payments; cash items only; no depreciation |
| Limitations | Estimates · time and cost · inflexible · can demotivate |