SEM 6 › Business Processes & Accounting Systems › Week 14
Business Processes & Accounting Systems · Week 14

Budgeting — Purposes, Budgetary Control, the Master Budget & Functional Budgets to the Cash Budget

What a budget is, its purposes and functions, steps in budgetary control, types of budgets and master budget components, sales forecasting, and the full LFT chain (sales → production → material usage → material purchases → labour → cash budget), plus limitations.

ITE36221 video · 38 min📄 Budgeting - Session 14.pdf📄 Practice – Budgeting.pdf

1What is a budget?

Definitions
  • Budget: a detailed plan, expressed in quantitative terms, that specifies how an organisation will acquire and use resources during a particular period. In the lecture's words, "a quantifiable action plan for a specified time period" 01:19.
  • Budgetary control: a system of planning and controlling cost.
  • Budgets flow from strategic planning. Every enterprise has goals: profitability, growth, public service.
  • Strategy aims at achieving and maintaining a competitive advantage through critical success factors: the key strengths most responsible for the organisation's success.
  • A budget is built on past activities: last year's figures plus planned changes 02:29.

Purposes & functions of budgeting 03:51

Purpose Meaning
Planning Plan annual operations: what and how much to produce and sell
Facilitating communication & coordination Departments share information, giving harmony between departments
Allocating resources Scarce resources go where they're needed
Managing financial & operating performance (control) Compare progress against the budget; take corrective action
Evaluating performance & providing incentives Motivates managers towards organisational goals

Steps in budgetary control

  1. Establish budgets
  1. Measure actual performance
  1. Compare actual with budget
  1. Analyse causes of variances & report

2Types of budgets

Budget What it is
Master budget A comprehensive set of budgets covering all phases of operations for a period
Operational budgets How operations will meet demand, using material, labour and overhead
Financial budget How the organisation will acquire its financial resources
Capital budget Plan for acquiring (and disposing of) capital assets
Cash budget Expected cash receipts and disbursements

The lecture groups them as functional budgets → master budget → cash budget 07:36.

Master budget components:

  • Operational:
  • sales budget
  • production budget
  • direct material budget
  • direct labour budget
  • overhead budget
  • budgeted cost of goods manufactured and sold
  • selling, general and admin budget (R&D, marketing, customer service)
  • Financial:
  • capital budget
  • cash budget
  • budgeted income statement
  • budgeted statement of financial position
  • budgeted statement of cash flows
Sales budgetProduction budgetMaterial usage → purchasesLabour & overhead budgetsCash budgetBudgeted income statement & balance sheet

Sales forecasting: the starting point

The sales budget drives everything else. The factors are:

  1. past sales levels and trends
  2. general economic trends
  3. economic trends in the industry
  4. other factors expected to affect industry sales
  5. political and legal events
  6. intended pricing policy
  7. planned advertising and promotion
  8. expected actions of competitors
  9. new products planned by the company or others
  10. market research studies

3The functional budgets: formats

Sales budget: Sales units × Selling price = Sales revenue
Production (units) = Budgeted sales + Closing finished goods − Opening finished goods
Material usage = Production units × Material per unit
Material purchases = Usage + Closing raw materials − Opening raw materials (× cost per unit)
Labour budget = Production units × Hours per unit × Rate per hour

Why subtract opening and add closing? Opening inventory is already made, so we don't produce it again. Closing inventory must also be made this period 13:53.

PDF example: quarterly sales & labour budgets (seasonal pattern)
Q1 Q2 Q3 Q4 Year
Sales units 15,000 5,000 10,000 20,000 50,000
× Rs 12 180,000 60,000 120,000 240,000 600,000
Units produced 14,000 5,500 11,000 19,500 50,000
× 0.2 labour hours 2,800 1,100 2,200 3,900 10,000
× Rs 10 per hour 28,000 11,000 22,000 39,000 100,000

4Full worked example: LFT company

  1. Sales & production budgets 14:37

Data:

Grade A Grade B
Expected sales (units) 50,000 10,000
Selling price Rs 6,000 Rs 8,000
Opening finished goods 1,000 500
Target closing finished goods 11,000 500

Sales budget:

A B Total
Units × price 50,000 × 6,000 10,000 × 8,000
Revenue 300m 80m 380m

Production budget:

A B
Sales units 50,000 10,000
Less: opening finished goods (1,000) (500)
Add: closing finished goods 11,000 500
Production 60,000 10,000
  1. Material usage & purchases 22:21

Per unit:

  • wood: 12 boards for both grades, Rs 70 per board
  • glass: A 6 sq ft, B 8 sq ft, Rs 100 per sq ft

Inventories:

  • wood: opening 70,000, closing 80,000
  • glass: opening 60,000, closing 20,000
Usage Wood (boards) Glass (sq ft)
Grade A: 60,000 × 12 / × 6 720,000 360,000
Grade B: 10,000 × 12 / × 8 120,000 80,000
Total usage 840,000 440,000
Value (× 70 / × 100) Rs 58.8m Rs 44m
Purchases Wood Glass
Usage 840,000 440,000
Less: opening (70,000) (60,000)
Add: closing 80,000 20,000
Purchase quantity 850,000 400,000
Purchase cost Rs 59.5m Rs 40m

Usage and purchases differ because of the inventory adjustments 29:21.

  1. Direct labour budget 30:43

Rs 200 per labour hour. A uses 4 hours and B uses 6 hours per unit.

A B Total
Production 60,000 10,000
Hours 240,000 60,000 300,000
Cost × 200 48m 12m 60m
  1. Cash budget 33:00

Assumptions:

  • opening cash Rs 3m
  • all sales are cash sales
  • material purchases are paid 100% within the year
  • labour is paid in the year
  • overheads are paid in cash
Rs m
Opening balance 3.0
Receipts: cash sales 380.0
Payments: material purchases (59.5 + 40) (99.5)
Direct labour (60.0)
Overheads (55.0)
Total payments (214.5)
Net surplus (380 − 214.5) 165.5
Closing balance (165.5 + 3) 168.5
Two slips in the video
  1. The question says overheads of Rs 50m, but the solution uses Rs 55m (that's what gives 214.5). With 50m, payments = 209.5, surplus = 170.5, and closing = 173.5.
  2. The video says the closing balance is 186.5m. That's an arithmetic slip: 165.5 + 3 = 168.5m.

Learn the method; check the numbers yourself.

5The cash budget: rules

Closing cash = Opening cash + Cash inflows − Cash outflows
  • It's prepared weekly or monthly so management can deal with shortages (arrange overdrafts or loans) or surpluses (invest them).
  • Only actual cash receipts and payments are included.
  • Depreciation is always excluded: it's not a cash flow.
  • Credit sales and purchases still outstanding at period end are excluded. Include cash when it's received or paid, e.g. a 30-day credit sale in March is received in April.
  • The closing balance of period 1 = the opening balance of period 2.
🧪 Try it — Budget chain builder (two products, one material)

Defaults: "other payments" = glass Rs 40m + overheads Rs 55m, which reproduces the 168.5m closing cash.

6Limitations of budgeting 36:08

  • Based on estimates and assumptions, so they lack accuracy.
  • Preparation takes time, cost and management effort.
  • Lack of flexibility: once fixed, budgets aren't changed for unexpected events (e.g. a COVID lockdown). This can demotivate employees who see the targets as unachievable 37:33.
  • Budgets can encourage budgetary slack and "spend it or lose it" behaviour.
Exam focus

Expect:

  1. Define a budget and budgetary control.
  2. Give the purposes and functions of budgets.
  3. List the steps in budgetary control.
  4. Name the master budget components.
  5. List sales forecasting factors.
  6. Prepare sales, production, material usage and purchases, labour and cash budgets. Remember the opening and closing stock adjustments. In the cash budget, exclude depreciation and account for credit timing.
  7. Give the limitations.

7Practice questions (course paper)

Q1: Cash budget, January to April 2019

Timing rules:

  • Customers pay two months after the sale
  • Suppliers are paid two months after the purchase
  • Wages are paid the next month
  • Other expenses are paid one month late
  • The machine is paid in 5 × 5,000 instalments from January
  • A dividend of 10,000 is paid in April
Jan Feb Mar Apr
Opening balance 15,000 18,985 23,795 22,975
Receipts from debtors 30,000 (Nov) 35,000 (Dec) 25,000 (Jan) 30,000 (Feb)
Total available 45,000 53,985 48,795 52,975
Creditors 15,000 20,000 15,000 20,000
Wages 3,200 2,500 3,000 2,400
Manufacturing, admin, selling (previous month) 2,815 2,690 2,820 2,890
Machinery instalment 5,000 5,000 5,000 5,000
Dividend — — — 10,000
Total payments 26,015 30,190 25,820 40,290
Closing balance 18,985 23,795 22,975 12,685
Q2: Receipts from customers (Saman Ltd)

Sales are read as Jan 90,000 · Feb 135,000 · Mar 220,000 · Apr 320,000 (the PDF's table is jumbled), and all sales are assumed to be on credit. Customers pay 25% in the month of sale, 50% the next month and 25% the month after.

Jan Feb Mar Apr
Jan sales 90,000 22,500 45,000 22,500
Feb sales 135,000 33,750 67,500 33,750
Mar sales 220,000 55,000 110,000
Apr sales 320,000 80,000
Receipts 22,500 78,750 145,000 223,750
Q3: Payments to material suppliers (Saman Ltd)

Materials cost 40% of sales: 36,000 · 54,000 · 88,000 · 128,000, with May at 160,000. Closing stock is half of next month's needs, and suppliers are paid one month later.

Jan Feb Mar Apr
Materials used 36,000 54,000 88,000 128,000
+ closing stock (½ of next month) 27,000 44,000 64,000 80,000
− opening stock 0 (27,000) (44,000) (64,000)
Purchases 63,000 71,000 108,000 144,000
Payment (one month later) 0 63,000 71,000 108,000

8Quick revision sheet

Concept Remember it as
Budget Quantified plan for acquiring and using resources over a period
Budgetary control System of planning and controlling cost
Purposes Plan · coordinate and communicate · allocate · control · evaluate and motivate
Control steps Set → measure → compare → analyse variances and report
Master budget All the budgets together → budgeted income statement and balance sheet
Production Sales + closing FG − opening FG
Purchases Usage + closing RM − opening RM
Labour Production × hours × rate
LFT answers Sales 380m · production A 60k, B 10k · wood 850k boards = 59.5m · glass 400k = 40m · labour 60m
Cash budget Opening + receipts − payments; cash items only; no depreciation
Limitations Estimates · time and cost · inflexible · can demotivate

?Self-check quiz